ARMAND E. LEMIRE CO. INC.
7 DARTMOUTH STREET
P.O. BOX 16454, HOOKSETT, NH 03106
PHONE (603) 625-5233 FAX (603) 625-5679
CHANGE ORDER #$
COMPANY T Buck Construction
ATTENTION Bruce Kenney
DATE 3/31/17
PROJECT Nashua Headworks
LOCATION Nashua NH
Hi Bruce, this change order is for repiping the Mens Rm toilet carriers,
pricing is as follows.
20’) 4” No Hub cast iron pipe @$20’
12) 4” NH couplings @$24.60 ea
1) 4” NH TY @$53
1) 4” x 2” NH TY @$35.60
2) 4” NH % bends @$34 ea
20’) 2” Copper DWV tubing @$14.21’
6) 2” Cop DWV 90’s @$49.13 ea
1) 2” Cop DWV TY @$69.21
2) 2” Cop DWV coup @$19.39 ea
3) 2” hanger assy’s @$15 ea
2) 4” hanger assy'’s @$15 ea
1) 2” Cop X 2”NH adapter w/clamps @$26
1) 3” x 12” core @$400
32) Additional labor hrs @$75 hr
Subtotal
AELCO 15% MU
Total amount of this change order is $5,105.74
$400.00
$295.20
$53.00
$35.60
$68.00
$284.20
$294.78
$69.21
$38.78
$45.00
$30.00
$26.00
$400.00
$2,400.00
$4,439.77
$665.97