T. Buck Construction, Inc.
249 Merrow Rd Auburn, ME 04210
207-783-6223 * FAX 207-783-3970
PROPOSAL 24
{Proposal Submitted to:
Wright-Pierce
Street:
230 Commerce Way, Suite 302
Phone:
Fax:
Job Name
(802) 431-1422 Date 4/3/2017
(866) 783-7101
Nashua Wastewater Treatment Facility Headworks Upgrade
City, State & Zip Code:
Portsmouth, NH 03801
Job Location:
Nashua NH
Engineer:
Andy Morrill
Job Phone:
ie hereby submit specifications and estimate for:
P
rovide labor, material and equipment to perform work to relocate 4” vent in existing wall that interferes with new wall.
Material
Labor
15% O&P
GC O&P 10%
TOTAL
$ 2,039.77
$_2,400.00,
$ 4,439.77
$ 665.97
$ 5,105.74
$ 443.98
$ 5,549.71
1) T Buck will request a 2 day extension to the contract completion time if this proposal is excepted
e Propose hereby to furnish material and labor complete in accordance with above specifications, for the sum of:
FIVE THOUSAND FIVE HUNDRED & FORTY NINE DOLLARS
All material is guaranteed to be as specified. All work to be completed in a
workmanlike manner according to standard practices. Any alteration or
deviation from above specifications involving extra costs will be executed only
Upon written orders, and will become an extra charge over and above the
estimate. All agreements contigent upon strikes, accidents or delays beyond
Authorized
Signature
Mark McPheters
Note: This proposal may be withdrawn
our control, Owner to carry fire, tornado and other necessary insurance. Our by us if not accepted within 5 days.
workers are fully covered by Workman's Compensation Insurance.
Acceptance of Proposal- The above prices, specifications and
he work as specified. Payment will be made as outlined above.
Date of acceptance Signature