ARMAND KH. LEMIRE CQ. INC,
7 DARTMOUTH STREET
P.O. BOX 16454, HOOKSETT, NH. 03106
PHONE (603) 625-5233 FAX (603) 625-5679
CHANGE ORDER #8
COMPANY T Buck Construction
ATTENTION Bruce Kenney
DATE 3/1/17
PROJECT Nashua Headworks
LOCATION Nashua NH
Hi Bruce, this change order is for the work described in WP-RFI-07, pricing
is as follows.
3’) Additional 26” FRP duct @$430' $1,290.00
Misc resins, tapes and supplies $125.00
24) Additional labor hrs @$75 hr $1,800.00
Additional freight on FRP $800.00
Controls add from ENE $2,450.00
Subtotal $6,465.00
AELCO 15% MU $969.75
Total amount of this change order is $7,434.75