16010-11
ELECTRICAL - GENERAL
Upon completion of the Work and before request for final payment, deliver to the
Engineer six (6) bound sets of full and complete directions pertaining to the
operation and maintenance of all equipment and systems installed under this
Contract in one final, complete submittal. These directions shall be neatly bound,
consist of typewritten on 8-1/2" x 11" sheets with index tabs, and shall be
accompanied by plans, diagrams, etc. of the work installed, parts lists, warranties,
test reports, etc. necessary for the guidance of the Owner in operating, altering or
repairing the installation. In addition to the foregoing, furnish the Engineer a written
statement from the Owner indicating that he is satisfied with the operating
instructions given.
Provide the Owner with a list of local service departments of duly authorized
distributors of materials and equipment of the type installed, which will stock the
manufacturer's standard parts, etc.
1.5 O&M REQUIREMENTS:
A.
Upon completion of the work and before request for final payment, deliver to the
Engineer six (6) bound sets of full and complete directions pertaining to the
operation and maintenance of all equipment and systems installed under this
Contract. These directions shall be typewritten on 8-1/2" x 11" sheets neatly bound
with index tabs, and shall be accompanied by plans, diagrams, etc., of the work
installed, parts lists, etc., necessary for the guidance of the Owner in operating,
altering or repairing the installation. In addition to the foregoing, furnish the
Engineer with a written statement from the Owner indicating that he is satisfied with
the operating instructions given.
Provide the Owner with a list of local service departments of duly authorized
distributors of materials and equipment of the type installed, which will stock the
manufacturer's standard parts, etc.
At the completion of the installation, provide six copies of reproducible Record
Drawings on sheets no less than 11"x17", indicating the final configuration of all
systems as they were installed. Symbols, equipment designations, etc., shall be
consistent with the Contract Documents. The following diagrams shall be included:
1. Panel diagrams on 11"x17" showing the front face and panel mounted
equipment with full listing of components including names, descriptions and
model numbers for each component. One copy of the panel diagrams will be
laminated for insertion into the pocket inside each control panel.
2. Point to Point terminal wiring diagrams for all field instruments, motor starters,
equipment drives, etc.
3. All drawing will be provided to the Owner as record drawings in either Autocad
DWG format or Adobe PDF format.
All pages shall be marked up indicating only relevant information pertaining to the
project and non-relevant information shall be crossed out.
Provide a section for the following sections for each equipment as applicable:
1. A description of operation
2. Installation
3. Emergency Operation Procedures
4. A troubleshoot guide with common failures and possible causes
5. A preventative maintenance schedule
13089K