01500-1
SECTION 01500
TEMPORARY FACILITIES AND CONTROLS
PART 1 - GENERAL
1.1
1.2
DESCRIPTION
A. Work Included:
1.
Provide and pay for all temporary applicable utilities required to properly
perform the Work at no additional cost to the Owner including the placement
and removal of the utilities.
Completely remove all temporary equipment and materials upon completion
of the Work and repair all damage caused by the installation of temporary
utilities.
Make all necessary applications and arrangements for electric power, light,
water, compressed air, laboratory vacuum air and other utilities with the local
utility companies as needed. Notify the local electric power company if
unusually heavy loads, such as welders, will be connected.
Provide temporary protection of existing concrete tanks and other unheated
concrete structures taken out of service for the General Contractor to complete
the Work as indicated on the Contract Documents in that area.
Contractor shall provide temporary ventilation during construction as required
to ensure a safe working environment. The temporary ventilation systems
shall address the following conditions, including but is not limited to: removal
of hazardous fumes from explosion-proof rated spaces (Class 1, Division 1
rated spaces), removal of paint fumes and other potentially toxic conditions
associated with the contractor's activities, and ventilation of confined spaces,
in compliance with all OSHA and State safety requirements.
QUALITY ASSURANCE
A. Requirements of Regulatory Agencies:
1.
2.
3.
4.
Obtain permits as required by local governmental authorities.
Obtain easements, when required, across private property other than that of
the Owner for temporary power service.
Comply with the latest National Electrical Code.
Comply with all local, State and Federal codes, laws, and regulations.
B. All temporary utilities are subject to the approval of the Engineer.