01340-2
SUBMITTALS
so, when the dimensions are of particular importance, or when so specified, the
drawings shall be certified by the manufacturer or fabricator as correct for the work.
Shop Drawings shall be submitted as a complete package by specification section,
unless otherwise reviewed and approved by the Engineer. It is the intent that all
information, materials and samples associated with each specification section be
included as a single submittal for the Engineer's review. Any deviation from this
requirement, such as submitting miscellaneous metals grouped by structure, shall be
requested in writing with an anticipated shop drawing breakdown/schedule prior to
any associated submittal.
The Contractor shall be responsible for the prompt and timely submittal of all shop
and working drawings so that there shall be no delay to the work due to the absence
of such drawings.
No material or equipment shall be purchased or fabricated especially for the
Contract until the required shop and working drawings have been submitted as
hereinabove provided and reviewed for conformance to the Contract
requirements. All such materials and equipment and the work involved in their
installation or incorporation into the Work shall then be as shown in and
represented by said drawings.
Until the necessary review has been made, the Contractor shall not proceed with
any portion of the work (such as the construction of foundations), the design or
details of which are dependent upon the design or details of work, materials,
equipment or other features for which review is required.
All shop and working drawings shall be submitted to the Engineer by and/or
through the Contractor, who shall be responsible for obtaining shop and working
drawings from his subcontractors and returning reviewed drawings to them. Hard
copies of shop drawings shall be of standardized sizes to enable the Owner to
maintain a permanent record of the submissions. Approved standard sizes shall be:
(a) 24 inches by 36 inches; (b) 11 inches by 17 inches, and (c) 11 inches by 8-1/2
inches. Provision shall be made in preparing the shop drawings to provide a
binding margin on the left hand side of the sheet. Shop drawings submitted other
than as specified herein may be returned for resubmittal without being reviewed.
Only drawings which have been checked and corrected by the fabricator should be
submitted to the Contractor by his subcontractors and vendors. Prior to submitting
drawings to the Engineer, the Contractor shall check thoroughly all such drawings
to satisfy himself that the subject matter thereof conforms to the Drawings and
Specifications in all respects. All drawings which are correct shall be marked with
the date, checker's name, and indication of the Contractor's approval, and then shall
be submitted to the Engineer.
If a shop drawing shows any deviation from the Contract requirements, the
Contractor shall make specific mention of the deviations in his letter of transmittal.
Shop Drawings that contain significant deviations that are not brought to the
attention of the Engineer may be subject to rejection.
Should the Contractor submit equipment that requires modifications to the
structures, piping, electrical conduit, wires and appurtenances, layout, etc., detailed
on the Drawings, he shall also submit details of the proposed modifications. If such
equipment and modifications are accepted, the Contractor, at no additional cost to
13089K