CONSTRUCTION SCHEDULES
4. Provide narrative report, including:
a. Discussion of problem areas, including current and anticipated delay
factors.
b. Corrective action taken, or proposed.
c. Description of revisions that may affect schedules.
1.2 SUBMITTALS
A. Submit updated schedules with each progress payment request.
B. Submit 4 copies of initial and updated schedules to the Engineer.
END OF SECTION