Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 6/7/2017 - P448

Finance Committee - Agenda - 6/7/2017 - P448

By dnadmin on Mon, 11/07/2022 - 10:24
Document Date
Wed, 06/07/2017 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 06/07/2017 - 00:00
Page Number
448
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__060720…

1.8

01150A-3
MEASUREMENT AND PAYMENT

INCIDENTAL WORK
Incidental work items for which separate payment is not made include (but are not
limited to) the following items:

A.

1.

OC PANDMAEYWN

11.
12.
13.
14.
15.

16.
17.
18.

19.

20.
21.
22.
23.
24.

25.

26.

27.
28.

Clearing, grubbing and stripping

Dust control

Dewatering

Clean-up

Erosion control

Loam, seeding, grading, liming, fertilization, mulching and watering

Pipe bedding and backfill

Compaction testing of backfill

Restoration of property, and replacement of fences, curbs, structures, sign
posts, guard rails, rock wall, mail boxes, traffic loop detectors and other minor
items disturbed by the construction activities

Coordination with the Owner, Utilities and others, including related inspection
cost (refer to Section 01050)

Utility crossings and relocations, unless payment is otherwise made

Traffic control plan and regulation

Project Signs

Routine flag person services

Trench boxes, steel and/or wood sheeting as required, including that left in
place

Project record documents

Materials testing

Construction schedules, bonds, insurance, shop drawings, warranties,
guarantees, certifications, and other submittals required by the Contract
Documents

Repair and replacement of water lines under two inches in size, culverts,
underdrains, rock lined drainage trenches in streets and other utilities damaged
by construction activities and corresponding proper disposal of removed
materials unless otherwise paid for

Cleaning, testing and disinfection of all water lines and appurtenances
Maintenance of all existing sewers flows and repair of existing sewer pipes
Final cleaning of sewers, force mains and storm drains

Final testing of manholes and sewers

Removal and disposal of existing sewer structures and pipe as and where
indicated in the Drawings

Temporary utilities for construction and to maintain existing service during
construction

Temporary utility services to buildings as required to maintain service during
construction

Quality assurance testing

Temporary construction and other facilities not to be permanently
incorporated into the Work necessary for construction sequencing and
maintenance of operations

13089K