O1150A-2
MEASUREMENT AND PAYMENT
encountered during the prosecution of the Work and until its final acceptance by the
Engineer, and for all risks of every description connected with the prosecution of
the work, except as provided herein, also for all expenses incurred in consequence
of the suspension of the work as herein authorized.
The payment of any partial estimate or of any retained percentage except by and
under the approved final invoice, in no way shall affect the obligation of the
Contractor to repair or renew any defective parts of the construction or to be
responsible for all damage due to such defects.
PAYMENT FOR INCREASED OR DECREASED QUANTITIES
A.
When alterations in the quantities of work not requiring supplemental agreements,
as hereinbefore provided for, are ordered and performed, the Contractor shall accept
payment in full at the Contract price for the actual quantities of work done. No
allowance will be made for anticipated profits. Increased or decreased work
involving supplemental agreements will be paid for as stipulated in such
agreements.
OMITTED ITEMS
A.
Should any items contained in the bid form be found unnecessary for the proper
completion of the work contracted, the Engineer may eliminate such items from the
Contract, and such action shall in no way invalidate the Contract, and no allowance
will be made for items so eliminated in making final payment to the Contractor.
PARTIAL PAYMENTS
A.
Partial payments shall be made monthly as the work progresses. Partial payment
shall be made subject to the provisions of the Supplemental and General
Conditions. Contractor's Partial Payment Requests shall be submitted in two parts;
one part for NHDES grant eligible quantities and one part for non-eligible
quantities. The breakdown of quantities will be determined by the Engineer.
PAYMENT FOR MATERIAL DELIVERED
A.
When requested by the Contractor and at the discretion of the Owner, payment may
be made for all or part of the value of acceptable, non-perishable materials and
equipment which are to be incorporated into bid items, have not been used, and
have been delivered to the construction site or placed in storage places acceptable to
the Owner. Payment shall be subject to the provisions of the General and
Supplementary Conditions.
No payment shall be made upon fuels, supplies, lumber, false work, or other
materials, or on temporary structures or other work of any kind which are not a
permanent part of the Contract.
FINAL PAYMENT
A.
The Engineer will make, as soon as practicable after the entire completion of the
project, a final quantity invoice of the amount of the Work performed and the value
of such Work. Owner shall make final payments of the sum found due less
retainages subject to the provisions of the General and Supplementary Conditions.
13089K