O01010A-4
SUMMARY OF WORK
shall be accomplished in strict accordance with applicable codes and standards and
the stricter of the Contractor's or Owner’s lock-out/tag-out procedures.
The Contractor shall have all materials and equipment on-site, and shall receive the
Owner's approval, prior to initiating work which will disrupt the facilities thermal
comfort and indoor air quality in occupied spaces.
Should the Contractor fail to complete the Work within the down-time specified
and should the Owner incur any actual costs directly or indirectly as a result thereof
that would otherwise not have incurred had the Contractor successfully completed
the Work within the specified down-time, the Contractor agrees to pay the Owner
such actual incurred costs. Such costs may include, but not be limited to, Owner's
actual costs of any additional maintenance and operations labor, material,
equipment, and chemical costs, or any other related actual costs incurred in order
for the Owner to keep the existing plant in normal operating condition.
The Contractor shall allow in the Bid reasonable time to accommodate operations at
the existing wastewater treatment plant, including the need for the Owner to
respond to emergencies. The Contractor shall not be eligible for additional
compensation due to interruptions of the Contractor's schedule, in order for the
Owner to respond to routine conditions.
There are specific requirements for construction sequencing and phasing. The
Contractor shall submit a construction sequence that recognizes the requirement
that the facility provide acceptable thermal comfort and indoor air quality in
occupied spaces.
The Contractor shall include the cost of all temporary facilities required to maintain
acceptable thermal comfort and indoor air quality in occupied spaces during the
construction period in his lump-sum bid price. The cost shall include the cost for
all labor, tools, equipment, materials and temporary systems, as necessary.
END OF SECTION