O1010A-2
SUMMARY OF WORK
e. Other appurtenances as shown on the Drawings and specified herein.
4. Remove and/or relocate equipment as indicated on the Drawings.
B. Related Work Specified Elsewhere:
1. Coordination: Section 01050
2. Construction Schedules: Section 01310.
C. Removals, Relocations and Rearrangements
1. Examine the existing site for the work of all trades which will influence the
cost of the work under the bid. This work shall include removals, relocations
and rearrangements which may interfere with, disturb or complicate the
performance of the work under the bid involving systems, equipment and
related service lines, which shall continue to be utilized as part of the finished
project. The Contractor is responsible for all coordination in this regard.
2. Provide in the bid a sufficient amount to include all removals, relocations,
rearrangements and reconnections herein specified, necessary or required to
provide approved operation and coordination of the combined new and
existing systems and equipment.
PART 2 - PRODUCTS
Not Applicable.
PART 3 - EXECUTION
3.1 MAINTAIN EXISTING WORKS
A. Minimize Interference
1. The Contractor shall at all times conduct his operations so as to interfere as
little as possible with existing works. The Contractor shall develop a
program, in cooperation with the Owner, Engineer, and interested officials,
which shall provide for the construction and putting into service of the new
works in the most orderly manner possible. This program shall be adhered to
except as deviations therefrom are expressly permitted.
2. Work of connecting with, cutting into, and reconstructing existing pipes or
structures shall be planned to interfere with the operation of the existing
facilities for the shortest possible time and when the demands on the facilities
best permit such interference. It may be necessary to work outside of normal
working hours to minimize interference. Before starting work which will
interfere with the operation of existing facilities, the Contractor shall do all
possible preparatory work and shall see that all tools, materials, and
equipment are made ready and at hand.
3. Any demolition of existing concrete, ductwork or equipment in the Control
Building shall require the Contractor to keep dust from entering the rest of the
building. Contractor shall provide temporary measures as required to control
the exposure of dust to the treatment plant personnel and the remainder of the
facility. The Contractor shall provide for continuous safe passage around
work for treatment facility personnel.
4. The Contractor shall not use the Owner’s bathrooms or kitchen facilities.