B-8.1
CERTIFICATE OF FINAL COMPLETION
Owner’s Project No. IFB0292-041017 Engineer’s Project No. —_13089K
Project HVAC Upgrades
Owner: City of Nashua, NH
Contractor:
Engineer: Wright-Pierce
Agreement Date:
Notice to Proceed Date:
Contractual Substantial Completion Date as modified by Change Orders:
Actual Substantial Completion Date:
Contractual Final Completion Date as modified by Change Orders:
The Work to which this Certificate applies has been inspected by authorized representatives of
Owner, Contractor, Engineer and NHDES, the punch list has been completed and the Work of
the Contract is hereby declared to be Finally Complete in accordance with the Contract
Documents on:
Date of Final Completion
This Certificate does not constitute an acceptance of any Work not in accordance with the
Contract Documents nor is it a release of Contractor’s obligation to complete the Work in
accordance with the Contract Documents. The Warranty for all Work completed subsequent
to the date of Substantial Completion expires one year from the date of this Final Acceptance.
Executed by Engineer on: , 20
By:
Contractor Accepts this Certificate of Final Completion on: ,20
By:
Owner Accepts this Certificate of Final Completion on: , 20
By:
13089K