Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 6/7/2017 - P297

Finance Committee - Agenda - 6/7/2017 - P297

By dnadmin on Mon, 11/07/2022 - 10:23
Document Date
Wed, 06/07/2017 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 06/07/2017 - 00:00
Page Number
297
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__060720…

16010-9
ELECTRICAL - GENERAL

c. Index Sheet - Listing the equipment being submitted utilizing equipment
designations, or symbols, indicated on the Contract Documents together
with the proposed manufacturer, style/ type and catalog number.

d. Manufacturer's scale or dimensioned drawings along with standard catalog
"cut" sheets. These cut sheets shall be marked up to indicate equipment,
sizes, types, etc., of equipment and all options being provided.

e. Equipment ratings, service clearances and configuration.

f. Listing of accessories to be furnished.

g. Single-line and schematic diagrams where applicable. All text and symbols
shall be easily legible and submitted on a 11"x17" sized drawing(s) as
necessary.

h. Refer to related sections of the specifications for special shop drawing
requirements for individual equipment types.

All Cut Sheets shall be marked up to indicate specific equipment, specific sizes,
specific types, etc., for all equipment and materials with all options provided
for this project. Catalog cut sheets not properly marked up, or are difficult
to read and understand as to what equipment or application that it is used for,
will be returned un-reviewed, for re-submittal.
The contract drawings have provided detailed customized schematic wiring
diagrams for all motor control center equipment as well as individual wall
mounted starters, control panels, etc. These are very detailed and a lot of effort
has been expended to compile these diagrams. The equipment
manufacturer/supplier of this equipment as specified shall be responsible to
provide the following detailed and customized schematic wiring diagrams.

a. A separate customized and detailed schematic for each piece of equipment
(i.e. RAS pumps No. 1, No. 2 and No. 3). Even though the schematic
appears to be same for this equipment a separate schematic for each will be
provided with the referenced title (1.e. RAS Pump No. 1, etc.) noted on the
respective schematic.

b. Each schematic shall indicate and show the specific devices (hand-off-auto,
run light, ETM, etc.) and a reference to where this is located.

c. All contacts and interlocks shall be identified as to their location.

d. All metering and interface devices such as digital metering, TVSS, lightning
protection, etc., shall be shown, identified, and dimensional heights from
bottom of equipment shall be noted.

e. Failure to provide the proper customized schematic wiring diagrams shall
be grounds for automatic rejection. Any delays, scheduling issues and
additional contract time and cost associated with these delays due to
equipment not being approved or being rejected for these reasons shall be
the responsibility of the Contractor.

Provide samples of such items as lighting fixtures, conduit, and wiring devices

upon request of the Engineer.

The following example is provided as a suggested formatting guideline. In addition
to expediting the review process, this formatting will help ensure that the vendor has
included all items applicable to the submittal, reduce the number of re-submittals and
ensure a quality project.