C. If the proper execution or results of any part of CONTRACTOR’s Work depends upon work performed by
others under this Article 7, CONTRACTOR shall inspect such other work and promptly report to ENGINEER in
writing any delays, defects, or deficiencies in such other work that render it unavailable or unsuitable for the
proper execution and results of CONTRACTOR’s Work. CONTRACTOR’s failure to so report will constitute
an acceptance of such other work as fit and proper for integration with CONTRACTOR’s Work except for latent
defects and deficiencies in such other work.
7.02 Coordination
A. If OWNER intends to contract with others for the performance of other work on the Project at the Site, the
following will be set forth in Supplementary Conditions:
1. The individual or entity who will have authority and responsibility for coordination of the activities among
the various contractors will be identified:
2. The specific matters to be covered by such authority and responsibility will be itemized; and
3. The extent of such authority and responsibilities will be provided.
B. Unless otherwise provided in the Supplementary Conditions, OWNER shall have sole authority and
responsibility for such coordination.
ARTICLE 8 - OWNER'S RESPONSIBILITIES
8.01 Communications to Contractor
A. Except as otherwise provided in these General Conditions, OWNER shall issue all communications to
CONTRACTOR through ENGINEER.
8.02 Replacement of ENGINEER
A. In case of termination of the employment of ENGINEER, OWNER shall appoint and whose status under the
Contract Documents shall be that of the former ENGINEER.
8.03 Furnish Data
A. OWNER shall promptly furnish the data required of OWNER under the Contract Documents.
8.04 Pay Promptly When Due
A. OWNER shall make payments to CONTRACTOR promptly when they are due as provided in paragraphs
14.02.C and 14.07.C.
8.05 Lands and Easements; Reports and Tests
A. OWNER's duties in respect of providing lands and easements and providing engineering surveys to establish
reference points are set forth in paragraphs 4.01 and 4.05. Paragraph 4.02 refers to OWNER's identifying and
making available to CONTRACTOR copies of reports of explorations and tests of subsurface conditions and
drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the
Site that have been utilized by ENGINEER in preparing the Contract Documents.