ENGINEER may require to enable ENGINEER to review the submittal for the limited purposes required by
paragraph 6.17.E. The numbers of each Sample to be submitted will be as specified in the Specifications.
C. Where a Shop Drawing or Sample is required by the Contract Documents or the schedule of Shop Drawings
and Sample submittals acceptable to ENGINEER as required by paragraph 2.07, any related Work performed
prior to ENGINEER’s review and approval of the pertinent submittal will be at the sole expense and
responsibility of CONTRACTOR.
D. Submittal Procedures
1. Before submitting each Shop Drawing or Sample, CONTRACTOR shall have determined and verified:
a. All field measurements, quantities, dimensions, specified performance criteria, installation
requirements, materials, catalog numbers, and similar information with respect thereto;
b. All materials with respect to intended use, fabrication, shipping, handling, storage, assembly, and
installation pertaining to the performance of the Work;
c. All information relative to means, methods, techniques, sequences, and procedures of construction and
safety precautions and programs incident thereto; and
d. CONTRACTOR shall also have reviewed and coordinated each Shop Drawing or Sample with other
Shop drawings and Samples and with the requirements of the Work and the Contract Documents.
2. Each submittal shall bear a stamp or specific written indication that CONTRACTOR has satisfied
CONTRACTOR’: obligations under the Contract Documents with respect to CONTRACTOR’s review and
approval of that submittal.
3. At the time of each submittal, CONTRACTOR shall give ENGINEER specific written notice of such
variations, if any, that the Shop Drawing or Sample submitted may have from the requirements of the
Contract Documents, such notice to be in a written communication separate from the submittal; and, in
addition, shall cause a specific notation to be made on each Shop Drawing and Sample submitted to
ENGINEER for review and approval of each such variation.
E. ENGINEER ’s Review
1. ENGINEER will timely review and approve Shop Drawings and Samples in accordance with the schedule
of Shop Drawings and Sample submittals acceptable to ENGINEER. ENGINEER’s review and approval will
be only to determine if the items covered by the submittals will, after installation or incorporation in the
Work, conform to the information given in the Contract Documents and be compatible with the design
concept of the completed Project as a functioning whole as indicated by the Contract Documents.
2.ENGINEER’s review and approval will not extend to means, methods, techniques, sequences, or
procedures of construction (except where a particular means, method, technique, sequence, or procedure of
construction is specifically and expressly called for the Contract Documents) or to safety precautions or
programs incident thereto. The review and approval of a separate item as such will not indicate approval of
the assembly in which the item functions.
3. ENGINEER’s review and approval of Shop Drawings or Samples shall not relieve CONTRACTOR from
responsibility for any variation from the requirements of the Contract Documents unless CONTRACTOR has
in writing called ENGINEER’s attention to each such variation at the time of each submittal as required by
paragraph 6.17.D.3 and ENGINEER has given written approval of each such variation by specific written
notation thereof incorporated in or accompanying the Shop Drawing or Sample approval; nor will any
GC - 31 of 57