D. Loading Structures:
CONTRACTOR shall not load nor permit any part of any structure to be loaded in any manner that will
endanger the structure, nor shall CONTRACTOR subject any part of the Work or adjacent property to stresses
or pressures that will endanger it.
E. To the fullest extent permitted by Laws and Regulations, CONTRACTOR shall indemnify and hold harmless
OWNER, ENGINEER, ENGINEER’s Consultant, and the officers, directors, partners, employees, agents, and
other consultants of each and any of them from and against all claims, costs, losses, and damages (including
but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court
or arbitration or other dispute resolution costs) arising out of or relating to any claim or action, legal or
equitable, brought by any such OWNER or occupant against OWNER, ENGINEER, or any other party
indemnified hereunder to the extent caused by or based upon CONTRACTOR’ performance of the Work.
6.12 Record Documents
A. CONTRACTOR shall maintain in a safe place at the Site one record copy of all Drawings, Specifications,
Addenda, Written Amendments, Change Orders,
Field Orders, and written interpretations and clarifications in good order and annotated to show changes made
during construction. These record documents together with all approved Samples and a counterpart of all
approved Shop Drawings will be available to ENGINEER for reference. Upon completion of the Work, these
record documents, Samples, and Shop Drawings will be delivered to ENGINEER for OWNER.
B CONTRACTOR shall mark up one set of paper prints to show the As-built conditions. They shall include all
the information shown on the Contract Drawings and a record of all deviations, modifications, or changes from
those Drawings, however minor, which were incorporated in the Work, all additional work not appearing on the
Contract Drawings and all changes which are made after final inspection of the Contract Work. These As-built
marked prints shall be kept current and available on the job site at all times. All changes from the Contract
Drawings which are made in the Work or additional information which might be uncovered in the course of
construction shall be accurately and neatly recorded as they occur by means of details and notes. No construction
work shall be concealed until it has been inspected, approved, and recorded. The As-built marked prints will be
jointly inspected for accuracy and completeness by the ENGINEER'S representative and a responsible
representative of the CONTRACTOR prior to submission of the monthly pay estimate. Failure to keep the
As-built marked prints on a current basis shall be sufficient justification to suspend pay estimates. The drawings
shall show the following information, but not be limited to:
1. The location of any utility lines or other installations of any kind or description known to exist within the
construction area. The location includes dimensions of permanent features.
2. The location and identification of all surface installations within 100 feet of the construction work.
3. The location and dimensions of any changes within the building or structure.
4. Correct grade or alignment of roads, structures, or utilities if any changes were made from Contract
Drawings.
5. Correct elevations if changes were made in site grading.
6. Changes in details or design or additional information obtained from working drawings specified to be
prepared or furnished by the CONTRACTOR including but not limited to fabrication, erection, installation
plans and placing details, pipe sizes, insulation material, dimensions or equipment foundations, etc.
7. The topography and grades of all drainage installed or affected as a part of the Work.