ENGINEER any conflict, error, ambiguity, or discrepancy which CONTRACTOR may discover and shall obtain
a written interpretation or clarification from ENGINEER before proceeding with any Work affected thereby:
however, CONTRACTOR shall not be liable to OWNER or ENGINEER for failure to report any conflict, error,
ambiguity, or discrepancy in the Contract Documents unless CONTRACTOR knew or reasonably should have
known thereof.
B. Preliminary Schedules: Within ten days after the effective Date of the Agreement (unless otherwise specified
in the General Requirements), CONTRACTOR shall submit to ENGINEER for its timely review:
1.A preliminary progress schedule indicating the times (numbers of days or dates) for starting and
completing the various stages of the Work, including any Milestones specified in the Contract Documents;
2. A preliminary schedule of Shop Drawing and Sample submittals which will list each required submittal
and the times for submitting, reviewing, and processing such submittal; and
3. A preliminary schedule of values for all of the Work which includes quantities and prices of items which
when added together equal the Contract Price and subdivides the Work into component parts in sufficient
detail to serve as the basis for progress payments during performance of the Work. Such prices will include
an appropriate amount of overhead and profit applicable to each item of Work.
C. Evidence of Insurance: Before any Work at the Site is started, CONTRACTOR and OWNER shall cach
deliver to the other, with copies to each additional insured identified in the Supplementary Conditions,
certificates of insurance (and other evidence of insurance which either of them or any additional insured may
reasonably request) which CONTRACTOR and OWNER respectively are required to purchase and maintain in
accordance with Article 5.
2.06 Preconstruction Conference
A. Within 20 days after the Contract times start to run, but before any Work at the Site is started, a conference
attended by CONTRACTOR, ENGINEER, and others as appropriate will be held to establish a working
understanding among the parties as to the Work and to discuss the schedules referred to in paragraph 2.05.B,
procedures for handling Shop Drawings and other submittals, processing Applications for Payment, and
maintaining required records.
2.07 Initial Acceptance of Schedules
A. Unless otherwise provided in the Contract Documents, at least ten days before submission of the first
Application for Payment a conference attended by CONTRACTOR, ENGINEER, and others as appropriate will
be held to review for acceptability to ENGINEER as provided below the schedules submitted in accordance with
paragraph 2.05.B. CONTRACTOR shall have an additional ten days to make corrections and adjustments and to
complete and resubmit the schedules. No progress payment shall be made to CONTRACTOR until acceptable
schedules are submitted to ENGINEER.
1. The progress schedule will be acceptable to ENGINEER if it provides an orderly progression of the Work
to completion within any specified Milestones and the Contract Times. Such acceptance will not impose on
ENGINEER responsibility for the progress schedule, for sequencing, scheduling, or progress of the Work nor
interfere with or relieve CONTRACTOR from CONTRACTOR’s full responsibility therefore.
2. CONTRACTOR’s schedule of Shop Drawing and Sample submittals will be acceptable to ENGINEER if
it provides a workable arrangement for reviewing and processing the required submittals.
3. CONTRACTOR’s schedule of values will be acceptable to ENGINEER as to form and substance if it
provides a reasonable allocation of the Contract Price to component parts of the Work.
GC - 9 of 57