City of Nashua, Public Works Division
Board of Public Works Meeting Date: June 19, 2017
Stephen Dookran, P.E., City Engineer
Engineering Department
Amherst Street Improvements — Charron Avenue to Diesel Road
Construction Phase Services
Amendment No. 1
To approve Amendment No. | to the construction phase engineering services
contract with Greenman-Pedersen, Inc. of Wilmington, MA for the Amherst
Street Improvements project in an amount of $77,865. Funding will be
through Department 160 Admin/Engineering; Fund: Bond & Contributions;
Activity: Amherst Street Road & Traffic Improvements.
Contract for Professional Services with Greenman-Pedersen, Inc. for
Construction Phase Services
In February 2016, GPI was hired to provide construction management,
construction administration and resident inspection for the four month
construction duration, as well as services for the warranty period of the contract.
Due to delays associated with the necessary utility pole relocations, the
construction contract was unable to be completed during the 2016 construction
season. The Contractor, Continental Paving, Inc. was granted a change order to
their contract in October 2016, to extend the completion date to July 15, 2017 and
they are on schedule to meet it. However, this results in the need to extend the
construction phase services contract with GPI to continue to provide resident
engineering for the additional two to three months (May, June and July).
It is recommended to add $23,718 to the contract, resulting in a revised contract
value of $101,583.