NASHUA FIRE 3 - GMP 001 RENO
Job: 121821866 - NASHUA FIRE 3 GMP 001 RENO
Gonnetie, Poge & Stone
TY Reference Type AdjQty Units AdjUnitCost Labor Material Equipment SubContr Other XtdCost
Thermal and Moisture Protection ( 07)
Fire Stopping & Sealants ( 07-715)
L 07.715.02 FIRE STOPPING & 1.00 LS 1,050.00 1,050.00 0.00 0.00 0.00 0.00 1,050.00
SEALANTS
INSTALLATION
M_ 07.715.04 FIRE STOPPING & 1.00 LS 500.00 0.00 500.00 0.00 0.00 0.00 500.00
SEALANTS MATERIALS
Subtotal: Fire Stopping & Sealants (07-715) $1,050.00 $500.00 $0.00 $0.00 $0.00 $1,550.00
Membrane Roofing ( 07-740)
S 07.740.02 075630 - FLUID 1.00 LS 22,933.00 0.00 0.00 0.00 22,933.00 0.00 22,933.00
APPLIED ROOFING
Subtotal: Membrane Roofing (07-740) $1.00 LS $22,933.00 $0.00 $0.00 $0.00 $22,933.00 $0.00 $22,933.00
Joint Sealers ( 07-760)
L 07.760.02 INTERIOR CAULKING 1.00 LS 1,050.00 1,050.00 0.00 0.00 0.00 0.00 1,050.00
INSTALLATION
M_ 07.760.04 INTERIOR CAULKING 1.00 LS 500.00 0.00 500.00 0.00 0.00 0.00 500.00
MATERIALS
Subtotal: Joint Sealers (07-760) $1,050.00 $500.00 $0.00 $0.00 $0.00 $1,550.00
Subtotal: Thermal and Moisture Protection $2,100.00 $1,000.00 $0.00 $22,933.00 $0.00 $26,033.00
(07)
Doors and Windows ( 08)
Steel Doors & Frames ( 08-805)
M_ 08.805.02 081113 - HOLLOW 1.00 EA 839.00 0.00 839.00 0.00 0.00 0.00 839.00
METAL FRAMES &
DOORS PURCHASE
L 08.805.22 081113 - HOLLOW 1.00 LS 357.00 357.00 0.00 0.00 0.00 0.00 357.00
METAL FRAMES &
DOORS INSTALL
M_ 08.805.26 087100 - DOOR FRAME 1.00 LS 933.00 0.00 933.00 0.00 0.00 0.00 933.00
& HW PURCHASE
Printed: 5/17/2017 4:20:22 PM Estimator: Barry Beauregard Bonnette, Page and Stone Corp. Page: 2