oJ we NASHUA FIRE 3 - GMP 001 RENO
Bonnatic, Poge & Stone
P;
Job: 121821866 - NASHUA FIRE 3 GMP 001 RENO
TY Reference Type AdjQty Units AdjUnitCost Labor Material Equipment SubContr Other XtdCost
Masonry ( 04)
Masonry ( 04-400)
S 04.400.16 MISC. MASONRY 1.00 LS 630.00 0.00 0.00 0.00 630.00 0.00 630.00
SUBOUT
M 04,400.18 MISC. MASONRY 1.00 LS 1,538.00 0.00 1,538.00 0.00 0.00 0.00 1,538.00
MATERIAL
Subtotal: Masonry (04-400) $0.00 $1,538.00 $0.00 $630.00 $0.00 $2,168.00
Subtotal: Masonry (04) $0.00 $1,538.00 $0.00 $630.00 $0.00 $2,168.00
Woods and Plastics ( 06)
Rough Carpentry ( 06-605)
M_ 06.605.02 ROUGH CARPENTRY 1.00 LS 1,400.00 0.00 1,400.00 0.00 0.00 0.00 1,400.00
L 06.605.04 ROUGH CARPENTRY 1.00 LS 5,796.00 5,796.00 0.00 0.00 0.00 0.00 5,796.00
LABOR
Subtotal: Rough Carpentry (06-605) $5,796.00 $1,400.00 $0.00 $0.00 $0.00 $7,196.00
Finish Carpentry ( 06-610)
L 06,610.04 FINISHED CARPENTRY 1.00 LS 2,100.00 2,100.00 0.00 0.00 0.00 0.00 2,100.00
LABOR
M 06.610.06 FINISH CARPENTRY 1.00 LS 1,000.00 0.00 1,000.00 0.00 0.00 0.00 1,000.00
Subtotal: Finish Carpentry (06-610) $2,100.00 $1,000.00 $0.00 $0.00 $0.00 $3,100.00
Rough Hardware ( 06-620)
M_ 06.620.02 ROUGH HARDWARE 1.00 LS 500.00 0.00 500.00 0.00 0.00 0.00 500.00
MATERIALS
Subtotal: Rough Hardware (06-620) $1.00 LS $500.00 $0.00 $500.00 $0.00 $0.00 $0.00 $500.00
Subtotal: Woods and Plastics (06) $7,896.00 $2,900.00 $0.00 $0.00 $0.00 $10,796.00
Printed: 5/17/2017 4:20:22 PM Estimator: Barry Beauregard Bonnette, Page and Stone Corp. Page: 1