NASHUA FIRE 3 GMP 002 no elevator
Job: 121821875 - NASHUA FIRE 3 GMP 002 no elevator
TY Reference Type AdjQty Units AdjUnitCost Labor Material Equipment SubContr Other XtdCost
Electrical ( 16)
Electrical ( 16-100)
S 16.100.02 DIVISION 26, 27 & 28 1.00 LS 73,225.00 0.00 0.00 0.00 73,225.00 0.00 73,225.00
ELECTRICAL & FIRE
ALARM SYSTEMS
Subtotal: Electrical (16-100) $1.00 LS $73,225.00 $0.00 $0.00 $0.00 $73,225.00 $0.00 $73,225.00
Subtotal: Electrical (16) $1.00 LS $73,225.00 $0.00 $0.00 $0.00 $73,225.00 $0.00 $73,225.00
Demo Cut and Patch ( 17)
Demo Cut & Patch ( 17-100)
L 17.100.04 DEMOLITION LABOR 1.00 LS 3,612.00 3,612.00 0.00 0.00 0.00 0.00 3,612.00
M 17.100.06 DEMOLITION 1.00 LS 1,500.00 0.00 1,500.00 0.00 0.00 0.00 1,500.00
MATERIALS
Subtotal: Demo Cut & Patch (17-100) $3,612.00 $1,500.00 $0.00 $0.00 $0.00 $5,112.00
Subtotal: Demo Cut and Patch (17) $3,612.00 $1,500.00 $0.00 $0.00 $0.00 $5,112.00
Allowances ( 18)
CM Contingency ( 18-100)
M 18.100.22 PERFORMANCE & 1.00 LS 11,550.00 0.00 11,550.00 0.00 0.00 0.00 11,550.00
PAYMENT BONDS
M 18.200.26 CM CONTINGENCY 1.00 LS 35,000.00 0.00 35,000.00 0.00 0.00 0.00 35,000.00
Subtotal: CM Contingency (18-100) $0.00 $46,550.00 $0.00 $0.00 $0.00 $46,550.00
Subtotal: Allowances (18) $0.00 $46,550.00 $0.00 $0.00 $0.00 $46,550.00