BPS
Bonnettc, Poge & Stone
NASHUA FIRE 3 GMP 002 no elevator
Job: 121821875 - NASHUA FIRE 3 GMP 002 no elevator
TY Reference Type AdjQty Units AdjUnitCost Labor Material Equipment SubContr Other XtdCost
Lockers ( 10-140)
L 10.140.08 GEAR LOCKERS 11.00 EA 52.50 577.50 0.00 0.00 0.00 0.00 577.50
INSTALL
Subtotal: Lockers (10-140) $11.00 EA $52.50 $577.50 $0.00 $0.00 $0.00 $0.00 $577.50
Subtotal: Specialties (10) $735.00 $500.00 $0.00 $0.00 $0.00 $1,235.00
Mechanical ( 15)
Mechanical ( 15-100)
S 15,100.02 DIVISION 23 - HVAC 1.00 LS 116,351.00 0.00 0.00 0.00 116,351.00 0.00 116,351.00
SYSTEM SUB-OUT
Subtotal: Mechanical (15-100) $1.00 LS $116,351.00 $0.00 $0.00 $0.00 $116,351.00 $0.00 $116,351.00
Plumbing ( 15-200)
S 15.200.02 DIVISION 22 - 1.00 LS 16,234.00 0.00 0.00 0.00 16,234.00 0.00 16,234.00
PLUMBING SUB-OUT
Subtotal: Plumbing (15-200) $1.00 LS $16,234.00 $0.00 $0.00 $0.00 $16,234.00 $0.00 $16,234.00
Fire Protection ( 15-400)
S 15.400.02 DIVISION 21 - FIRE 1.00 LS 20,180.00 0.00 0.00 0.00 20,180.00 0.00 20,180.00
SUPRESSION SYSTEM
SUB-OUT
Subtotal: Fire Protection (15-400) $1.00 LS $20,180.00 $0.00 $0.00 $0.00 $20,180.00 $0.00 $20,180.00
Subtotal: Mechanical (15) $0.00 $0.00 $0.00 $152,765.00 $0.00 $152,765.00
Printed: 5/31/2017 8:57:45 AM
Estimator: Barry Beauregard
Page: 15