133 tes
Bonnette, Poge & Stone
TY Reference Type
NASHUA FIRE 3 GMP 002 no elevator
Job: 121821875 - NASHUA FIRE 3 GMP 002 no elevator
AdjQty Units AdjUnitCost Labor Material Equipment SubContr Other XtdCost
Miscellaneous Steel ( 05-540)
S 05.540.14 055000 - METAL 1.00 LS 5,100.00 0.00 0.00 0.00 5,100.00 0.00 5,100.00
FABRICATIONS
SUBOUT
M_ 05.540.18 MISC. STEEL BID 1.00 LS 1,500.00 0.00 1,500.00 0.00 0.00 0.00 1,500.00
Subtotal: Miscellaneous Steel (05-540) $0.00 $1,500.00 $0.00 $5,100.00 $0.00 $6,600.00
Cold Formed Metal Framing ( 05-580)
S 05.580.02 054000 - COLD 1.00 LS 59,195.00 0.00 0.00 0.00 59,195.00 0.00 59,195.00
FORMED METAL
FRAMING SUBOUT
Subtotal: Cold Formed Metal Framing (05- $1.00 LS $59,195.00 $0.00 $0.00 $0.00 $59,195.00 $0.00 $59,195.00
580)
Subtotal: Metals (05) $0.00 $1,500.00 $5,000.00 $102,795.00 $0.00 $109,295.00
Woods and Plastics ( 06)
Rough Carpentry ( 06-605)
M_ 06.605.02 ROUGH CARPENTRY 1.00 LS 2,394.00 0.00 2,394.00 0.00 0.00 0.00 2,394.00
L 06.605.04 ROUGH CARPENTRY 1.00 LS 10,164.00 10,164.00 0.00 0.00 0.00 0.00 10,164.00
LABOR
Subtotal: Rough Carpentry (06-605) $10,164.00 $2,394.00 $0.00 $0.00 $0.00 $12,558.00
Finish Carpentry ( 06-610)
L 06.610.04 FINISHED CARPENTRY 1.00 LS 2,100.00 2,100.00 0.00 0.00 0.00 0.00 2,100.00
LABOR
M_ 06.610.06 FINISH CARPENTRY 1.00 LS 2,500.00 0.00 2,500.00 0.00 0.00 0.00 2,500.00
Subtotal: Finish Carpentry (06-610) $2,100.00 $2,500.00 $0.00 $0.00 $0.00 $4,600.00
Printed: 5/31/2017 8:57:45 AM
Estimator: Barry Beauregard
Page: 10