ons
tay NASHUA FIRE 3 GMP 002 no elevator
Bonnette, Poge & Stone
Job: 121821875 - NASHUA FIRE 3 GMP 002 no elevator
TY Reference Type AdjQty Units AdjUnitCost Labor Material Equipment SubContr Other XtdCost
M 03,380.15 TIES & ACCESSORIES 4.00 TN 65.00 0.00 260.00 0.00 0.00 0.00 260.00
Subtotal: Concrete Reinforcement (03-380) $0.00 $3,988.00 $0.00 $2,800.00 $0.00 $6,788.00
Miscellaneous Concrete ( 03-390)
L 03.390.02 MISC. CONCRETE 1.00 LS 2,500.00 2,500.00 0.00 0.00 0.00 0.00 2,500.00
LABOR
M_ 03.390.04 MISC. CONCRETE 1.00 LS 1,500.00 0.00 1,500.00 0.00 0.00 0.00 1,500.00
MATERIALS
L 03,390.10 HOUSEKEEPING PADS 1.00 LS 1,176.00 1,176.00 0.00 0.00 0.00 0.00 1,176.00
L
M_ 03.390.12 HOUSEKEEPING PADS 1.00 LS 500.00 0.00 500.00 0.00 0.00 0.00 500.00
M
L 03.390.23 VINYLEX DUMBELL 1.00 LS 756.00 756.00 0.00 0.00 0.00 0.00 756.00
WATERSTOP @
ELEVATOR INSTALL
M 03.390.24 VINYLEX DUMBELL 1.00 LS 75.00 0.00 75.00 0.00 0.00 0.00 75.00
WATERSTOP @
ELEVATOR PURCHASE
L 03.390.33 SET COLUMN ANCHOR 8.00 EA 4.20 33.60 0.00 0.00 0.00 0.00 33.60
BOLTS LABOR
M 03,390.34 SET COLUMN ANCHOR 8.00 EA 3.50 0.00 28.00 0.00 0.00 0.00 28.00
BOLTS PURCHASE
Subtotal: Miscellaneous Concrete (03-390) $4,465.60 $2,103.00 $0.00 $0.00 $0.00 $6,568.60
Subtotal: Concrete (03) $7,499.33 $24,270.90 $5,000.00 $25,036.70 $0.00 $61,806.93
Masonry ( 04)
Masonry ( 04-400)
E 04.400.02 MASONRY EQUIPMENT 1.00 LS 5,000.00 0.00 0.00 5,000.00 0.00 0.00 5,000.00
RENTAL
S 04,400.08 048100 - MASONRY 1.00 LS 27,700.00 0.00 0.00 0.00 27,700.00 0.00 27,700.00
SUBCONTRACTOR
Subtotal: Masonry (04-400) $0.00 $0.00 $5,000.00 $27,700.00 $0.00 $32,700.00
Printed: 5/31/2017 8:57:45 AM Estimator: Barry Beauregard Page: 8