BPS NASHUA FIRE 3 GMP 002 no elevator
PY ae Oe eeu
|
Job: 121821875 - NASHUA FIRE 3 GMP 002 no elevator
TY Reference Type AdjQty Units AdjUnitCost Labor Material Equipment SubContr Other XtdCost
L 03,345.24 SLAB VAPOR BARRIER 2,034.00 SF 0.32 640.71 0.00 0.00 0.00 0.00 640.71
LABOR
M 03.345.26 SLAB VAPOR BARRIER 2,034.00 SF 0.25 0.00 508.50 0.00 0.00 0.00 508.50
MATERIAL
L 03.345.28 CURE SLAB ON GRADE 1,598.00 SF 0.21 335.58 0.00 0.00 0.00 0.00 335.58
LABOR
M 03.345.30 CURE SLAB ON GRADE 1,598.00 SF 0.10 0.00 159.80 0.00 0.00 0.00 159.80
MATERIAL
L 03.345.32 SAW CUT SLAB ON 220.00 LF 2.10 462.00 0.00 0.00 0.00 0.00 462.00
GRADE
M_ 03.345.34 SAW CUT SLAB ON 220.00 LF 1.00 0.00 220.00 0.00 0.00 0.00 220.00
GRADE M
S$ 03.345.38 FLASH FLOORS SOG 1,598.00 SF 0.35 0.00 0.00 0.00 559.30 0.00 559.30
L 03.345.40 BOX OUT COLUMNS L 2.00 EA 25.00 50.00 0.00 0.00 0.00 0.00 50.00
M_ 03.345.42 BOX OUT COLUMNS M 2.00 EA 20.00 0.00 40.00 0.00 0.00 0.00 40.00
L 03.345.44 CONCRETE FILL AT 2.00 EA 10.00 20.00 0.00 0.00 0.00 0.00 20.00
COLUMN BOX OUTS
M 03.345.46 CONCRETE FILL AT 2.00 EA 5.00 0.00 10.00 0.00 0.00 0.00 10.00
COLUMN BOX OUTS M
L 03,345.48 EXPANSION / 180.00 LF 2.10 378.00 0.00 0.00 0.00 0.00 378.00
ISOLATION JOINT SOG
LABOR
M 03.345.50 EXPANSION / 180.00 LF 1.00 0.00 180.00 0.00 0.00 0.00 180.00
ISOLATION JOINT SOG
MATERIAL
M 03.345.64 REINFORCEMENT 1,598.00 SF 0.65 0.00 1,038.70 0.00 0.00 0.00 1,038.70
SUPPORT AT SLAB ON
GRADE
Subtotal: Concrete Slab on Grade (03-345) $1,886.29 $8,940.00 $0.00 $12,089.30 $0.00 $22,915.59
Printed: 5/31/2017 8:57:45 AM Estimator: Barry Beauregard Page: 6