BPS NASHUA FIRE 3 GMP 002 no elevator
Bonnetta. Page & Stone
Job: 121821875 - NASHUA FIRE 3 GMP 002 no elevator
TY Reference Type AdjQty Units AdjUnitCost Labor Material Equipment SubContr Other XtdCost
Concrete ( 03)
Concrete ( 03-300)
E 03.300.02 CONCRETE 1.00 LS 5,000.00 0.00 0.00 5,000.00 0.00 0.00 5,000.00
EQUIPMENT RENTAL
Subtotal: Concrete (03-300) $1.00 LS $5,000.00 $0.00 $0.00 $5,000.00 $0.00 $0.00 $5,000.00
Spread Footings ( 03-305)
S$ 03.305.51 CONCRETE FOOTING 1.00 LS 9,600.00 0.00 0.00 0.00 9,600.00 0.00 9,600.00
& WALL INSTALL
M 03.305.53 CONCRETE FOOTING 20.00 CY 110.00 0.00 2,200.00 0.00 0.00 0.00 2,200.00
3,000 REDIMIX
PURCHASE
Subtotal: Spread Footings (03-305) $0.00 $2,200.00 $0.00 $9,600.00 $0.00 $11,800.00
Low Wall Concrete ( 03-320)
M_ 03.320.05 CONCRETE WALL 20.00 CY 110.00 0.00 2,200.00 0.00 0.00 0.00 2,200.00
3,000 REDIMIX
PURCHASE
Subtotal: Low Wall Concrete (03-320) $20.00 CY $110.00 $0.00 $2,200.00 $0.00 $0.00 $0.00 $2,200.00
Pier Concrete ( 03-335)
M 03,335.17 CONCRETE COLUMN 3.00 CY 110.00 0.00 330.00 0.00 0.00 0.00 330.00
FOOTING 3,000
REDIMIX PURCHASE
Subtotal: Pier Concrete (03-335) $3.00 CY $110.00 $0.00 $330.00 $0.00 $0.00 $0.00 $330.00
Concrete Slab on Grade ( 03-345)
S 03,345.06 SLAB ON GRADE & 1.00 LS 10,830.00 0.00 0.00 0.00 10,830.00 0.00 10,830.00
SLAB ON DECK
SUBOUT
M_ 03.345.08 SLAB ON GRADE 4,000 38.00 CY 178.50 0.00 6,783.00 0.00 0.00 0.00 6,783.00
REDIMIX PURCHASE
S$ 03,345.12 SLAB ON GRADE 1.00 TN 700.00 0.00 0.00 0.00 700.00 0.00 700.00
REINFORCEMENT
INSTALL
Printed: 5/31/2017 8:57:45 AM Estimator: Barry Beauregard Page: 5