City of Nashua, Public Works Division
Board of Public Works Meeting Date: June 22, 2017
Noelle Osborne, Plant Operations Supervisor
Wastewater Department
Pump Station Upgrades Design Services — Final Design
To approve the contract award for final design phase of the Pump Station
Upgrades to Woodard & Curran of Portland, ME in amount not to exceed
$461,569. Funding will be through: Department: 169 - Wastewater; Fund:
Wastewater; Activity: Pump Station Upgrades.
Pump Station Upgrades ~ Final Design Phase-Scope of Work and Fee
There are fourteen (14) City owned pump stations throughout Nashua. These
pump stations are all the original installations which range from 30-55 years
old. Complete upgrades of all pump station are needed, which includes new
communications to the Wastewater Treatment Facility’s SCADA program.
Woodard & Curran was hired initially to perform a preliminary evaluation and
provide recommendations of the upgrades needed at all 14 locations.
Following the preliminary phase work they completed a 30% design of this
project. This work included most of the survey and geotechnical work needed
to move into final design.
Woodard and Curran will next complete the final design, prepare construction
bidding documents and assist with the construction bidding phase. We
recommend continuing this work with W&C since they have performed the
previous work competently and within budget. Their costs for the final design
was negotiated and is now reasonable for the scope of work involved. This
project is eligible for a 20% State Aid Grant from the New Hampshire
Department of Environmental Services.