CHANGE ORDER
PROJECT: Upgrade of Sewer System Siphon Covers
OWNER’S CONTRACT NO:__RFP1087-120916
EXECUTED CONTRACT DATE: February 1, 2017
DATE OF ISSUANCE: June 27, 2017 EFFECTIVE DATE: Upon City Approval
OWNER: City of Nashua, NH
OWNER’s Purchase Order NO.: 131720
CONTRACTOR: William P, Davis, Excavation LLC
ENGINEER: DPW Engineering
You are directed to make the following changes in the Contract Documents:
Description:
> Replace existing vortex structure top slab with new center access top slab with hatch
> Time Extension to complete Change Order #2
Attachment:
» William P. Davis, LLC Change Order #002 Proposal dated May 24, 2017
Change Order #2 1 of 2
Upgrade of Sewer System Siphon Covers