We expect to meet all calendar benchmarks included in the project schedule. Upon completion
of final design and bidding, we anticipate the work will be followed by construction
administration and we will work with the City to develop that scope.
Figure — Estimated Project Schedule
Project Highlights
Month - Year
Jul-17
Aug-17
Sep-17
Oct-17
Nov-17
Dec-17 :} Jan-17 | Feb-17
Mar-17
Apr-17 =>
Dec-19
Final Design
60% Review Meeting
90% Review Meeting
NHDES Permit Applications
100% Bid Documents Complete
Regulatory Review
NHDES Design Review Submittal
100% Bid Documents Complete
Bidding
Advertising
Pre-bid Conference
Receive Bids
Bid Evaluation and Recommendation
Construction
City of Nashua (P228730.19)
Attachment 1
Woodard & Curran
June 5, 2017