CHANGE IN CONTRACT PRICE:
Original Contract Price
$49,875.00
CHANGE IN CONTRACT TIMES:
Original Contract Times
Substantial completion: April 28, 2017
Ready for final payment: May 26, 2017
Net changes from previous Change Orders
$4,996.20
Net change from previous Change Orders
none
Contract Price prior to this Change Order
$54,871.20
Contract Times prior to this Change Order
Substantial completion: April 28, 2017
Ready for final payment: May 26, 2017
Net Increase (deerease} of this Change Order
$16,617.50
Net Increase (deerease} of this Change Order
Substantial completion: September 1, 2017
Ready for final payment: September 31, 2017
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
$71,488.70 Substantial completion: September 1, 2017
Ready for final payment: September 31, 2017
RECOMMENDED: ACCEPTED: APPROVED:
By: By: By:
DPW Engineering Name Mayor Jim Donchess
Engineer Contractor Owner
(Authorized Signature) (Authorized Signature) (Authorized Signature)
Date: Date: Date:
Change Order #2 2 of 2
Upgrade of Sewer System Siphon Covers