We try to give 2-3 days notice
Do you have specific requirement in mind for QA/QC reporting. Does it require
the benchsheet?
We only require that you meet NELAC standards. We do not need to sec
the bench sheet in the report.
Can you share the name of the lab that currently holds the contract?
The City of Nashua does not have a current contract for this type of
testing.
Can you share the winning bid of the latest contract?
The City of Nashua does not have a current contract for this type of
testing.
Should a Quality Assurance Manual be provided upon bid submission or when
the contract is awarded?
We will request the QA manual of the lowest bidder to assist in
determining qualification prior to the award of the contract
What metals are required to be analyzed for?
Al, As,B,Cd,Cr,Cu,Pb,Hg,Ni,Se,Ag,Zn