B-6.1
CHANGE ORDER
No. 5
PROJECT: _Headworks Upgrade DATE OF ISSUANCE:
OWNER: City of Nashua
229 Main St, Nashua, NH 03062
CONTRACTOR: T-Buck Construction, Inc. OWNER’s Project No.
CONTRACT FOR: _ Headworks Upgrade ENGINEER — Wright-Pierce
ENGINEER’s Project No. _ 13089
You are directed to make the following changes in the Contract Documents.
Description: Clean Headworks & Additional Concrete Removal
Purpose of Change Order: Additional concrete removal required in "short" channel to install new mechanical
bar screen. Multiple wet weather events required the wet well/lower screen room to be cleaned after each
event. This work delayed installation of the screen.
Justification: Work was not included in original contract documents.
Attachments: Back-up docurnentation.
CHANGE IN CONTRACT PRICE
CHANGE IN CONTRACT TIME
Original Contract Price Original Contract Time
$ _2,848,222.00
455
(days or date)
Previous Change Orders
$ 91,120.11
Net change from previous Change Orders
42
. (days)
Contract Price prior to this Change Order
Contract Time prior to this Change Order
$ _2,939,342.11 497
‘ (days or date)
Net Increase of this Change Order Net Increase this Change Order
$ 17,452.98 21
(days)
Contract Time with all Change Orders
518 days (Substantial Completion = 9/22/2017,
Final Completion = 10/23/2017)
(days or date)
Contract Price with all approved Change Orders
$ _2,956,795.09
This document will become a supplement to the CONTRACT and all provisions will apply hereto. The
attached Contractor’s Revised Project Schedule reflects increases or decreases in Contract Time as
authorized by this Change Order,
Stipulated price and time adjustment includes all costs and time associated with the above described change.
Contractor waives all rights for additional time extension for said change. Contractor and Owner agree that
the price(s) and time adjustment(s) stated above are equitable and acceptable to both parties.
RECO; ED: APPROVED:
By: By:
Engineer Owner
3/0}
Date Date
13089A