CHANGE IN CONTRACT PRICE:
Original Contract Price
$1,729,148.30
CHANGE IN CONTRACT TIMES:
Original Contract Times
Substantial completion: October 15, 2017
Ready for final payment: October 31, 2017
Net changes from previous Change Orders
50.00
Net change from previous Change Orders
None
Contract Price prior to this Change Order
$1,729,148.30
Contract Times prior to this Change Order
Substantial completion: October 15, 2017
Ready for final payment: October 31, 2017
Net Increase (deerease} of this Change Order
$474,205.00
Net Increase (deerease} of this Change Order
Substantial completion: none
Ready for final payment: none
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
$2,203,353.30 Substantial completion: see below
Ready for final payment: see below
RECOMMENDED: ACCEPTED: APPROVED:
By: By: By:
DPW Name Mayor Jim Donchess
Engineering Contractor Owner
(Authorized Signature) (Authorized Signature) (Authorized Signature)
Date: Date: Date:
Change Order # 1 2 of 2