CHANGE ORDER
No.1
PROJECT: 2017 Paving Program
OWNER’S CONTRACT NO. : IFB0660-030217
EXECUTED CONTRACT DATE: April 21, 2017
DATE OF ISSUANCE: July 14, 2017 EFFECTIVE DATE: Upon City Approval
OWNER: City of Nashua, NH
OWNER’s Purchase Order NO.: 133147
CONTRACTOR: E J Paving
ENGINEER: DPW Engineering
You are directed to make the following changes in the Contract Documents:
Description: The general scope of Change Order 1 is shown below. All work shall be done in
accordance with the 2017 Street Paving Program Contract requirements.
A. Mill, shim, and overlay Tinker Rd.
Mill depth = 2.5”
Temporary striping
Shim = 3/8” PG64-28 superpave 1” thick
Place temporary pavement markers
All castings will need to be adjusted/replaced as directed
Top = '4” PG64-28 superpave 1.5” thick
Final striping
>A AO op
B. Install 500 linear feet of straight granite curbing on Fairway St.
The addition of the work on Tinker Rd. and the installation of curbing on Fairway St. will not impact
the Substantial Completion Date of October 15, 2017 or the Final Completion Date of October 31,
2017.
Attachment: EJ Paving Schedule of Values dated July 14, 2017
Change Order # 1 1 of 2
2017 Paving Program