Summary
CHANGE IN CONTRACT PRICE:
Original Contract Price
CHANGE IN CONTRACT TIMES:
Original Contract Times
Substantial completion: October 15, 2017
Ready for final payment: October 31, 2017
$2,627,902.45
Net changes from previous Change Orders Net change from previous Change Orders
$0.00 None
Contract Price prior to this Change Order Contract Times prior to this Change Order
$2,627,902.45 Substantial completion: October 15, 2017
Ready for final payment: October 31, 2017
Net Increase (decrease) of this Change Order Net Increase (decrease) of this Change Order
$2,058,630.00 Substantial completion: November 17, 2017
Ready for final payment: December 15, 2017
Contract Price with all approved Change Orders Contract Times with all approved Change Orders
34,686,532.45 Substantial completion: November 17, 2017
Ready for final payment: December 15, 2017
RECOMMENDED: ACCEPTED: APPROVED:
By: vo By Bye
DPW Name Mayor Jim Donchess
Engineering Contractor Owner
(Authorized Signature) (Authorized Signature) (Authorized Signature)
Date: Date: Date: _
Change Order # 2 2 of 2
2016 Paving Program