CHANGE ORDER
No. 2
PROJECT: 2016 Paving Program
OWNER’S CONTRACT NO. : IFB0660-020316
EXECUTED CONTRACT DATE: March 18, 2016
DATE OF ISSUANCE: July 26, 2017 EFFECTIVE DATE: Upon City Approval
OWNER: City of Nashua, NH
OWNER’s Purchase Order NO.: 126118
CONTRACTOR: Brox Industries Inc.
ENGINEER: DPW Engineering
You are directed to make the following changes in the Contract Documents:
Description: Change Order 2 is to add approximately 6.5 miles of residential streets to the 2016
Paving Program Contract. These selected residential streets will require 2-inch mill & overlay or shim
& overlay as directed by the Engineer.
Attachment(s):
> 2017 Pavement Management ~ Phase II : List of Streets
> FY16 Street Paving Program, Change Order No. 2 (Phase II) — Schedule of Values
Change Order # 2 1 of 2
2016 Paving Program