Summary
CHANGE IN CONTRACT PRICE:
Original Contract Price
$327,423.94
CHANGE IN CONTRACT TIMES:
Original Contract Times
Substantial completion: October 15, 2017
Ready for final payment: October 31, 2017
Net changes from previous Change Orders
$0.00
Net change from previous Change Orders
None
Contract Price prior to this Change Order
$327,423.94
Contract Times prior to this Change Order
Substantial completion: October 15, 2017
Ready for final payment: October 31, 2017
Net Increase (deerease} of this Change Order
$150,000.00
Net Increase (deerease} of this Change Order
Substantial completion: 45 calendar days
Ready for final payment: 45 calendar days
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
$477,423.94 Substantial completion: November 30, 2017
Ready for final payment: December 15, 2017
RECOMMENDED: ACCEPTED: APPROVED:
By: By: By:
DPW Name Mayor Jim Donchess
Engineering Contractor Owner
(Authorized Signature) (Authorized Signature) (Authorized Signature)
Date: Date: Date:
Change Order # 1
2017 Pavement Preservation
Maintenance Program
2 of 2