CHANGE ORDER
No.}t
PROJECT: 2017 Pavement Preservation Maintenance Program
OWNER’S CONTRACT NO. : IFB0660-040617
EXECUTED CONTRACT DATE: June 13, 2017
DATE OF ISSUANCE: September 27, 2017 EFFECTIVE DATE: Upon City Approval
OWNER: City of Nashua, NH
OWNER’s Purchase Order NO.: 134276
CONTRACTOR: Sealcoating, Inc
ENGINEER: DPW Engineering
You are directed to make the following changes in the Contract Documents:
Description: Change Order 1 is for an additional $150,000 to the contract for the purpose of applying
crack sealing to City streets. This budget will be used for items associated with crack sealing items:
405.11 (Crack Sealing); 618.6 (Uniformed Officers); 618.7 (Flaggers); and 619.1 (Maintenance of
Traffic). Streets selected for treatment and use of the bid items listed will be finalized and approved by
the Engineer prior to performing the work.
Change Order # 1
1 of 2
2017 Pavement Preservation
Maintenance Program