Summary
CHANGE IN CONTRACT PRICE:
Original Contract Price
$2,627,902.45
CHANGE IN CONTRACT TIMES:
Original Contract Times
Substantial completion: October 15, 2017
Ready for final payment: October 31, 2017
Net changes from previous Change Orders
$2,058,630.00
Net change from previous Change Orders
None
Contract Price prior to this Change Order
$4,686,532.45
Contract Times prior to this Change Order
Substantial completion: November 17, 2017
Ready for final payment: December 15, 2017
Net Increase (decrease) of this Change Order
$137,945.00
Net Increase (deerease) of this Change Order
Substantial completion: 0 days
Ready for final payment: 0 days
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
$4,824,477.45 Substantial completion: November 17, 2017
Ready for final payment: December 15, 2017
RECOMMENDED: ACCEPTED: APPROVED:
By: By: By:
DPW Name Mayor Jim Donchess
Engineering Contractor Owner
(Authorized Signature) (Authorized Signature) (Authorized Signature)
Date: Date: Date:
Change Order # 3 2 of 2
2016 Paving Program