ARMAND I. LEMIRE Co., INC.
7 DARTMOUTH STREET
P.O. BOX 16454, HOOKSETT, NH 03106
PHONE (603) 625-5233 FAX (603) 625-5679
CHANGE ORDER #10 REVISED 8/21/17
COMPANY 'T Buck Construction
ATTENTION Bruce Kenney
DATE TIT? oe
PROJECT Nashua Headworks
LOCATION | Nashua NH _
Hi Bruce, this change order is for the relocation of an existing 2” dom HW
line that interferes with the HV installation.
6) 2” cop 90’s @$50.21 ea $301.26
10’) 2” type L coppwer tubing @$17.36' $173.60
12’) 2” x 1” wall ASJ fiberglass insulation @$9 $108.00
6) PVC Zeston ftg covers @$7.55 ea $45.30
3) Hanger assemblies @$15 ea $45.00
16) Additional labor hrs @$75 hr $1,200.00
Subtotal $1,873.16
AELCO 15% MU $280.97
Tota! amount off this change order is $2,154.13*
“lf isolation vaives do not hold, additional time for shutdown/drain wili
be based on $75 per hr.
MECHANICAL CONTRACTORS — COMMERCIAL, INDUSTRIAL & RESIDENTIAL
- WBE/DBE CERTIFIED ©