PART IH - PRICE SUMMARY
COMPETITOR'S CATALOG LISTINGS, IN-HOUSE ESTIMATES, PRIOR QUOTES
13. (Indicate basis for price comparison)
MARKET
PRICE (S)
PROPOSED
PRICE
PART IV - DIRECT LABOR BY CATEGORY
14. INSERT THE APPROPRIATE WORK CATEGORY IN THE TABLE BELOW. WORK CATEGORIES WOULD INCLUDE BUT
NOT BE LIMITED TO THOSE CATEGORIES SHOWN IN THE CONTRACT DOCUMENTS SUCH AS DESIGN, SURVEY,
SUBSURFACE, CADASTRAL, 0&M MANUAL, ADMINISTRATION, INSPECTION, RECORD DWGS, START-UP, SPECIAL
SERVICES, ETC.
Work category
Phase > ! 2 3 4 re Rate Cost
Project Manager 28 22 17 5 72 72 5184
Lead Engineer 42 58 14 10 124 51 6272
Staff Engineer 100 116 32 30 278 3] 8618
Lead Designer 8 27 5 2 42 39 1638
Staff Designer 23 119 27 14 183 32 5856
Technician
Clerical 20
Total - Sy Cost $27,568
Page 2 of 2