Background
Mr. Choi has over 11 years of experience as an electrical designer, staff and lead engineer
responsible for the design, layout of all electrical design documents in industrial,
commercial, manufacturing power generation and distribution plants. Mr. Choi is
experienced in utilizing Electrical Transient Analysis Program software for load flow,
short circuit, arc flash analysis, protective device coordination studies and power system
modeling. Also has special experience with AutoCAD and AutoCAD Electrical for
creating and updating electrical interconnect wiring diagram and wire schedules.
Experience
Prolerized New England Co. Mega Shredder Project (Schnitzer Northeast) — Everett, MA
Electrical designer responsible for installation of a 9O0OHP Car Shredder motor, new
facility substation and distribution system.
Harvard University Steam Plant Upgrade Project — Cambridge, MA
Electrical designer responsible for design of No 2 and No 6 Fuel Oil Yard electrical
conduit routing plan and interconnect wiring diagram.
One Bryant Park Cogeneration Plant Project — Manhattan, NY
Electrical Designer responsible for the installation of a new 5 MW Solar Mercury 50 Gas
Turbine located in new high rise office building in Manhattan. Project included
interconnection design with the local utility's grid (Con Edison).
Pfizer Global Manufacturing Gas Turbine Installation Project — Groton, CT
Electrical designer and commissioning engineer responsible for design and installation of
a 10.7 MW Solar Mars 100 Gas Turbine. Design motor control centers, electrical panels,
entire electrical interconnect wiring diagram and installation of cable tray throughout the
plant.
VPSSA Swanton Peaker Plant Project No. 10 - Swanton, VT
Electrical designer responsible for design of interconnect wiring diagrams on electrical
distribution system, switchyard/substation for 2 qty 18.9 MW GE Gas Turbine peaking
plant.
P&G Gillette SBMC Cogeneration Facility Upgrade Proiect — Boston MA
Staff electrical engineer responsible for removing an existing boiler and install a 7.2 MW
Solar Taurus 70 Gas Turbine including design of interconnect wiring diagrams for gas
turbine generator, electrical distribution and auxiliaries. Commissioning engineer
responsible for the gas turbine generator start-up, switchgear, relay protection system,
MCC and PLC based load shed and import control system.
P&G Gillette Hazardous Area Classification Audit Project — Boston, MA
Staff electrical engineer responsible for visiting hazardous classified area within P&G
facility and examine to determine if the existing installation of equipments and wiring
methods in those areas are in compliance with the National Electrical Code (NFPA 70)