Project Number: 228730 WWTE SCADA Upgrades
Issue Date: August 2017 Nashua, NH
SECTION 40 67 00
CONTROL SYSTEM EQUIPMENT PANELS AND RACKS
PART 1-— GENERAL
1.01 SUMMARY
A. Section Includes
1.
Provide all wiring, labor, tools, materials, and equipment necessary to
furnish, install, and test control panels and enclosures in accordance with
this Section and applicable reference standards listed in Article 1.03.
The Contractor shall furnish, deliver, unload, and power up control panels
and enclosures as specified on the Drawings.
Related Requirements
a. Refer to other Specifications in Division 40 for equipment to be
furnished but requiring installation and startup to reflect complete
integration of the systems, instrumentation, interlocking,
interfacing, and installation under this Section.
b. Refer to Specifications in Division 26, Electrical for wiring
standards and practices.
1.02 PRICE AND PAYMENT PROCEDURES
A. Measurement and payment requirements: per Division 01 General Requirements.
1.03 REFERENCES
A. Reference Standards
1.
2.
National Fire Protection Association 79, Annex "D" Standards, (NFPA)
National Electrical Code, (NEC)
National Electrical Manufacturer's Association Standards, (NEMA)
American Society for Testing and Materials, (ASTM)
Operational Safety and Health Administration Regulations, (OSHA)
Underwriters’ Laboratory, Inc., (UL)
American National Standards Institute, Inc. (ANSI)
Factory Mutual (FM)
CONTROL SYSTEM EQUIPMENT PANELS AND RACKS
WOODARD & CURRAN 40 67 00-1