Project Number: 228730 WWTE SCADA Upgrades
Issue Date: August 2017 Nashua, NH
D.
Provide permanent plastic name tag indicating load for each feeder for all junction
boxes, handholes and manholes. Label all process motor wires to yard equipment
in handholes and manholes.
3.05 TESTS & SETTINGS
A.
Provide the services of an independent Testing Agency to perform the specified
tests for the following systems:
1. Ground resistance. The Testing Company shall perform all testing in
accordance with National Electrical Testing Association (NETA)
standards and procedures. All testing results shall be submitted on NETA
forms and the testing data shall be certified by the respective Agency. Test
results shall indicate recommended action for a sub-par test results.
Results shall list recommended test values that should be obtained for new
installation.
Provide necessary material, equipment, labor and technical supervision to perform
and complete the Electrical Acceptance Tests as required.
Acceptance tests as herein specified are defined as those tests and inspections
required to determine that the equipment involved is acceptable as delivered to the
job Site, that the equipment may be energized for final operational tests and is in
accordance with the Specifications.
Final acceptance of the equipment and/or workmanship will depend upon
performance characteristics as determined by the subject tests, in addition to
complete operation tests, on all electrical equipment to show that it will perform
the functions for which it was designed.
If the test and inspection data submitted should indicate deficiencies in the
operation of the electrical apparatus or in the manufacturer thereof, the Contractor
shall promptly implement the necessary adjustments, corrections, modifications
and/or replacements necessary to be made to meet the specified requirements.
Upon completion of the remedial Work, the Testing Agency shall repeat all of the
tests on components previously found deficient on the first test or any additional
test if they be required. It shall be the responsibility and obligation of the
Contractor to have all remedial Work accomplished as may be required by second
and/or additional tests.
COMMON WORK RESULTS FOR ELECTRICAL
WOODARD & CURRAN 26 05 00-13