Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 11/15/2017 - P280

Finance Committee - Agenda - 11/15/2017 - P280

By dnadmin on Mon, 11/07/2022 - 10:19
Document Date
Wed, 11/15/2017 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 11/15/2017 - 00:00
Page Number
280
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__111520…

Project Number: 228730 WWTE SCADA Upgrades
Issue Date: August 2017 Nashua, NH

8. When specified in individual Specification Sections, require manufacturer
to provide field representative to be present at Site to inspect, check and
approve equipment or system installation before start up, and to supervise
placing equipment or system in operation.

C. Starting, Adjusting, and Balancing

1. Supply necessary equipment, material, construction power, and
consumables (except for those provided by Owner) needed to startup and
fully test the Work and replenish the same until Substantial Completion is
achieved. Contractor may utilize Owner’s operating spare parts, such use
requiring timely replacement at Contractor’s expense.

2. Coordinate as required for conduct of independent testing.

3. Perform specified and required adjusting and balancing concurrently to the
maximum extent possible on individual equipment and systems and prior to
startup and commissioning/performance testing.

D. Startup and Commissioning/Performance Testing

1. Conduct startup and commissioning/performance tests and perform
pressure and leakage tests per the Specifications to demonstrate the Work
meets the requirements of the Contract Documents, satisfies the Owner’s
requirements.

2. Prepare and submit a written startup and commissioning/performance
testing procedures no later than 60 days prior to start of testing for review
and final test procedures no later than 30 days prior to start of testing.
Submit a staffing request for Owner’s operations and maintenance
personnel.

3. Calibrate test equipment and instrumentation on Site or provide acceptable
certificate of calibration conducted within 30 days of testing.

4. Complete functional testing prior to initiating the startup and
commissioning/performance testing as specified.

5. Complete specified startup and commissioning/performance tests prior to
Substantial Completion. Owner and Engineer will witness Performance
Testing. Notify Owner and Engineer in writing at least 7 days prior to
starting any startup and commissioning/performance testing. Coordinate
for witnessing of tests by required regulatory representatives.

6. Submit written test reports per subparagraph 1.03.C.7.b and Paragraph
1.03.D above.

OVERALL GENERAL REQUIREMENTS
WOODARD & CURRAN 01 11 05-25