Project Number: 228730 WWTE SCADA Upgrades
Issue Date: August 2017 Nashua, NH
3.03 STARTUP, TESTING, AND COMMISSIONING
A. Spare Parts
1. Provide spare parts required for construction, startup, testing and
commissioning of the Work prior to achievement of Substantial
Completion, including spare parts for flushing and consumable supplies
such as bolts, nuts, gaskets, filters, insulating tape, etc., normally consumed
in the construction, commissioning and testing.
2. If spare parts are purchased by Owner, Contractor shall have the right to use
the spare parts purchased by Owner provided that such spare parts are
replaced prior to Substantial Completion at Contractor’s expense.
Replacement spare parts, replaced by Contractor, shall be new, unused and
identical as the original spare part used.
B. Checkout and Starting Systems
1. Coordinate schedule for startup and operation of various equipment and
systems with Owner.
2. Notify Owner 7 days before startup of each major piece of equipment or
system, including a staffing request for Owner’s operations and
maintenance personnel required to adequately and safely support each
specific start-up and operation activity.
3. Verify that each system or piece of equipment item has been assembled,
constructed, or completed in accordance with the Contract Documents and
capable of functioning as intended.
4. Verify that each piece of equipment or system has been checked for proper
lubrication, drive rotation, magnetic center alignment, belt tension, control
sequence, or other conditions which may cause damage.
5. Verify that each piece of equipment or system has successfully completed
construction testing and cold commissioning, including hydrostatic testing,
loop checks, relay checks, calibration, and continuity checks and that all
tests, meter readings, and specified electrical characteristics agree with
those required by the equipment or system manufacturer.
6. Verify wiring and support components for equipment are complete and
tested.
7. Execute start up under supervision of responsible manufacturers’
representative or Contractor's personnel in accordance with manufacturers'
instructions utilizing Owner’s qualified operations and maintenance staff
trained by Contractor.