Project Number: 228730 WWTE SCADA Upgrades
Issue Date: August 2017 Nashua, NH
4. Coordinate related Work at the Site.
5. Coordinate completion and cleanup of Work of separate sections in
preparation for Substantial Completion and for portions of Work designated
for Owner's partial occupancy.
6. Regular working hours are set forth in the General and Supplemental
Conditions.
7. Comply with sequencing requirements included in Section 01 11 00.
B. Record Documents
1. Contractor shall maintain in a safe place at the Site one record copy of all
Drawings, Specifications, Addenda, Change Orders, Work Change
Directives, Field Orders, and written interpretations and clarifications in
good order and annotated to show changes made during construction. These
record documents together with all approved Samples and a counterpart of
all approved Shop Drawings will be available to Engineer for reference. and
submitted at final completion per Paragraph 1.03.D above.
2. Store Record Documents separate from documents used for construction.
Record information concurrent with construction progress.
3. Legibly mark each item to record description of actual equipment and
material installed and actual construction on approved submittals, including
the following.
a. Manufacturer's name and equipment and material model and
number
b. Material and equipment substitutions or alternates utilized
C. Approved changes
d. Field changes of dimension and detail
e. Details not on original Contract Documents or Shop Drawings
4. Submit final record documents as specified in Paragraph 1.03.D above in
accordance with subparagraph 1.03.C.8. above. Engineer’s review of the
final Application for Payment and accompanying documentation and all
maintenance and operating instructions, schedules, guarantees, bonds,
certificates of inspection, tests and approvals, and other documentation
required to be delivered at final completion will be only be to determine
generally that the content complies with the requirements of, and in the case
of certificates of inspections, tests and approvals, that the results certified
indicate compliance with, the Contract Documents.
OVERALL GENERAL REQUIREMENTS
WOODARD & CURRAN 01 11 05-23