Project Number: 228730 WWTE SCADA Upgrades
Issue Date: August 2017 Nashua, NH
2. As a minimum, Contractor shall:
a. have been regularly and actively engaged in similar Work as
described in the Contract Documents, operating under the same
business name and business organization structure, for the last 5
years on at least 5 projects;
b. have successfully completed at least 3 projects involving
construction of similar facilities in the same state as the Project
covered by the Contract Documents;
C. have a full-time project manager in responsible charge of the Work
with at least 10 years’ experience as project manager on comparable
projects; and
d. carry at least the insurance coverage and amounts required in the
Contract.
PART 2— PRODUCTS
2.01 SOURCE QUALITY CONTROL
A. General
1. Subject material and equipment furnished under these Contract Documents
to a complete factory testing program as specified.
2. Shop Drawings and submittals: reviewed by Engineer before initiating
testing program.
3. Perform checks and tests in accordance with manufacturer's
recommendations and referenced standards.
4. Evaluate test results and advise Owner immediately of any discrepancy
between test results and test limits or the failure of any device or system
under test. Include test limits for acceptability applicable to each test on the
certified test records.
5. Record test information, including the evaluation of testing results, on forms
approved by Owner and Engineer.
B. Independent Testing Agency Certification
1. If specified, furnish certificates from an independent testing agency.
2. Independent testing agency to certify that material and equipment
components have been examined and tested and are in conformance with
the requirements specified in the Contract Documents.
OVERALL GENERAL REQUIREMENTS