Project Number: 228730 WWTE SCADA Upgrades
Issue Date: August 2017 Nashua, NH
4. The date of achieving Substantial Completion is the date set forth in the
Certificate of Substantial Completion that is accepted and signed by the
Owner.
5. During the period between Substantial Completion and the date for Final
Completion, Contractor shall be given access to correct items on the Punch
List and achieve Final Completion.
6. Upon written notice from Contractor that the entire Work or an agreed
portion thereof is complete using the Notice of Completion form attached
to this section, Engineer will promptly make a final inspection with Owner
and Contractor and will notify Contractor in writing of all particulars in
which this inspection reveals that the Work is incomplete or defective.
Contractor shall immediately take such measures as are necessary to
complete such Work or remedy such deficiencies.
7. Final Completion shall have been achieved when Contractor has, in the
opinion of Engineer, satisfactorily completed all corrections identified
during the final inspection and has delivered, in accordance with the
Contract Documents, documents including maintenance and operating
instructions, schedules, guarantees, warranties, bonds, certificates or other
evidence of insurance, certificates of inspection, marked up record
documents, and other required documents, and Engineer has indicated that
the Work is complete in accordance with the Contract Documents including
the following.
a. Final cleaning has been conducted and Contractor equipment and
supplies including waste materials have been removed from the Site
and legally disposed of.
b. Inspections required by Laws and Regulations are complete.
Certificates and permits to occupy and operate have been issued if
required.
C. Spare parts, maintenance and extra materials have been delivered in
quantities specified to Project Site and stored as directed.
d. A Final Application for Payment has been submitted to the Engineer
identifying total adjusted Contract Price, previous payments, and
balance due along with required documentation including:
1) all documentation called for in the Contract Documents
2) consent of the surety, if any, to final payment
3) a list of all Claims against Owner that Contractor believes
are unsettled