Finance Committee - Agenda - 11/15/2017 - P270

By dnadmin on Mon, 11/07/2022 - 10:19
Document Date
Wed, 11/15/2017 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 11/15/2017 - 00:00
Page Number
270
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__111520…

Project Number: 228730
Issue Date: August 2017

D.

WWTE SCADA Upgrades
Nashua, NH

Part 4: Other Project documents and certificates, including
the following:

° Certificates
° Photocopies of warranties
Closeout Procedures
1. Substantial Completion shall have been achieved when Work is complete,

systems are successfully operating, and final testing has been successfully
completed and Contractor considers the entire Work ready for its intended
use; a full inventory of the spare parts and special tools purchased by the
Owner are replenished and in the custody of the Owner; the Site has been
restored to the satisfaction of the Owner; an inspection of the Work has been
completed by the Engineer and the Owner; and an updated Punch List is
provided. The Contractor shall have sole care, custody, and control of the
Work until achievement of Substantial Completion.

Contractor shall notify Owner and Engineer in writing that the entire Work
is substantially complete (except for items specifically listed by Contractor
as incomplete) using the Notice of Substantial Completion form attached to
this section and request that Engineer issue a certificate of Substantial
Completion. Promptly after Contractor’s notification, Owner, Contractor,
and Engineer shall make an inspection of the Work to determine the status
of completion. If Engineer does not consider the Work substantially
complete, Engineer will notify Contractor in writing giving the reasons
therefor.

If Engineer considers the Work substantially complete, Engineer will
deliver to Owner a tentative certificate of Substantial Completion which
shall fix the date of Substantial Completion using the Certificate of
Substantial Completion included in the Contract Documents with Punch
List attached. Owner shall have 7 days after receipt of the tentative
certificate during which to make written objection to Engineer as to any
provisions of the certificate or attached list. If, after considering such
objections, Engineer concludes that the Work is not substantially complete,
Engineer will, within 14 days after submission of the tentative certificate to
Owner, notify Contractor in writing, stating the reasons therefor. If, after
consideration of Owner’s objections, Engineer considers the Work
substantially complete, Engineer will, within said 14 days, execute and
deliver to Owner and Contractor a definitive certificate of Substantial
Completion (with a revised Punch List) reflecting such changes from the
tentative certificate as Engineer believes justified after consideration of any
objections from Owner.

OVERALL GENERAL REQUIREMENTS

WOODARD & CURRAN 01 11 05-15